Deephams Sewage Treatment Works Upgrade

Adams Hendry Consulting Ltd

 

Submission Summary:
The £250m Deephams STW Upgrade has fully upgraded London's 4th largest STW through a programme delivered by collaborative planning, design and engineering, and:
- was delivered alongside full operation of the original STW
- has eliminated off-site odour emissions
- has improved water quality in the Salmons Brook and the River Lee
- has improved local enjoyment of private and public open space
- will provide for climate change resilience
- will provide critical support in a major area of regeneration for homes and business
- provided new construction employment, skills and training opportunities in the local area